Nexus Events
Nexus Sprint Review
Integrated product review · Timebox: ≤4 hours (1-month Sprint)
Overview
The Nexus Sprint Review replaces individual team Sprint Reviews. The entire Nexus presents the Integrated Increment to stakeholders. This is one review for the whole product — demonstrating that the combined work of all teams creates integrated value.
Event Ownership
Owned / Facilitated By
Product Owner (content) / NIT Scrum Master (facilitation)
PO frames the review around product progress and the Product Goal
NIT SM facilitates the session, ensures stakeholder engagement, and manages the timebox
Teams demo their portions of the Integrated Increment — showing how their work integrates
PO captures feedback and adapts the Product Backlog based on stakeholder input
Who Should Be Present
All Nexus Teams
Present and demo the Integrated Increment. Show how their work integrates with other teams’ work
Product Owner
Frames progress, facilitates discussion, captures feedback, adapts the Product Backlog
Stakeholders
Provide feedback on the Integrated Increment. Share market context and emerging needs
NIT
Demonstrates integration quality. Shows how the product works as a whole, not as separate pieces
Preparation Checklist
01NIT: Ensure the Integrated Increment is working and demo-ready in a realistic environment
02Teams: Prepare demo of their integrated contributions
03PO: Prepare product progress context and discussion topics
04NIT SM: Invite stakeholders, prepare facilitation plan